Estimated Timeline

  • Day 0
    • Preorders Close
  • 1-2 Weeks: Business
    • Deposit made
    • Factory contract signed [IN PROGRESS]
  • 1-6 Weeks: Design
    • Review our designs with factory specifications [IN PROGRESS]
    • Tooling
  • 2-6 Weeks: Sourcing
    • Source plastics
    • Color batching
    • Order materials
    • Lead time for factory availability
  • 3-10 Weeks: Sampling
    • Aesthetics
    • Durability
    • Usability
    • 1-2 weeks for aesthetic changes
    • 2-4 weeks for structural changes
    • This may repeat several times
    • Receive samples
    • Review samples
    • Provide feedback
    • Changes made
    • Repeat
  • 4-12 Weeks: Production
    • Manufacturing
    • Quality control
  • 2-4 Weeks: Fulfillment
    • Packaging
    • Shipping

ESTIMATES DO NOT INCLUDE HOLIDAYS. HOLIDAYS WILL ADD 4-6 WEEKS.

OVERSEAS SHIPPING IS VERY DIFFICULT TO ESTIMATE DUE TO GLOBAL FREIGHTING CONDITIONS.