- Day 0
Preorders Close
- 1-2 Weeks: Business
Deposit made- Factory contract signed [IN PROGRESS]
- 1-6 Weeks: Design
- Review our designs with factory specifications [IN PROGRESS]
- Tooling
- 2-6 Weeks: Sourcing
- Source plastics
- Color batching
- Order materials
- Lead time for factory availability
- 3-10 Weeks: Sampling
- Aesthetics
- Durability
- Usability
- 1-2 weeks for aesthetic changes
- 2-4 weeks for structural changes
- This may repeat several times
- Receive samples
- Review samples
- Provide feedback
- Changes made
- Repeat
- 4-12 Weeks: Production
- Manufacturing
- Quality control
- 2-4 Weeks: Fulfillment
- Packaging
- Shipping
ESTIMATES DO NOT INCLUDE HOLIDAYS. HOLIDAYS WILL ADD 4-6 WEEKS.
OVERSEAS SHIPPING IS VERY DIFFICULT TO ESTIMATE DUE TO GLOBAL FREIGHTING CONDITIONS.